Observa-Dome Laboratories, Inc: Observatory Installation

Observa-Dome Laboratories designed and fabricated the 30-foot diameter dome atop the Science Center at an elevation of approximately 96 feet above the ground. We carefully analyzed the wind loadings and structural requirements of the dome and engineered a model that would be reassembled on the ground and lifted on top of the building. In approximately two weeks, the prefabricated sections were reassembled and lifted on top of the building to complete the observatory. 

Take a closer look at the installation process and see a small piece of the colossal effort and careful planning required to successfully install this essential piece. 

New Orlando Science Center Installation, Orlando, Florida

On Friday, February 2, 1996, final acceptance testing was successfully completed for a model 30.375 Observa-Dome at the New Orlando Science Center in Orlando, Florida.

The 30-foot diameter Observa-Dome sits atop the central part of the building at an elevation of approximately 96 feet above the ground. Being an integral part of a public building, it was necessary to demonstrate that our Observa-Dome structure will withstand all applicable wind loadings as required by local and state building codes. To this end, the latest finite analysis computer modeling programs were utilized by our structural engineers, registered in the State of Florida, to provide structural calculations demonstrating the capability of this Observa-Dome. Because of the complexity of working atop an unfinished roof at this level, it was decided to reassemble the dome on the ground adjacent to the facility and employ a crane to lift it on top of the building.

Monday

Monday, January 22, 1996, the prefabricated Observa-Dome sections arrived in a 48-foot enclosed van and were unloaded on-site. Reassembly began immediately, beginning with the dome tension ring and supporting arch structure.

Monday

Tuesday

Tuesday, Observa-Dome personnel attached the dome skin sections to the dome tension ring and arches. The remaining skin flange bolts, “T” gasket, and slit frame splice plates were installed on Wednesday. Shutter-actuating tracks and tubes were also bolted into place.

Tuesday

Thursday

Thursday, January 25, the dome shutter sections were bolted together, lifted into place, and bolted to the track mechanism. All shutter actuating mechanisms, including the cable, pulleys, gear motor, limit switches, and reversing relays, were installed and tested. Additionally, an interior rubber shutter flashing was installed. The base angle ring sections, horizontal and vertical casters, grout, electrical power bars, and azimuth drive motors were hoisted onto an intermediate roof level.

Thursday

Friday

Friday, the base angle ring and dome casters were set in place atop the building. Leveled and rounded to plus or minus 1/16 of an inch, the base ring was secured to the building steel structure with 48–1/2-inch anchor bolts.

Friday

Saturday

Saturday, the space between the base ring and steel structure was filled with a non-shrink grout to provide further support.

Saturday

Monday

Monday, January 29, the dome was given a final washing on the ground to remove any fingerprints and dirt incurred during reassembly.

Monday

Tuesday

Tuesday, final preparations for lifting the dome atop the building were completed, and an area was cleared between the dome and the building in which to assemble and place the crane early Wednesday morning.

Tuesday

Wednesday

Wednesday morning, 10 am, the 30-foot diameter Observa-Dome was lifted into place 96 feet above the ground and over 100 feet from the edge of the building. A 300-ton capacity hydro crane with a 235-foot boom was used to make the lift, requiring approximately 30 minutes.

Wednesday

Thursday

By the end of Thursday, all flashings, skirting, and electrical components had been installed. All rotating dome functions were tested in preparation for the final acceptance testing scheduled for Friday morning.

Thursday

Friday

Friday morning, February 2, 1996, all final acceptance testing was accomplished successfully and witnessed by the Directors of the New Orlando Science Center, construction management, and by the project architect. The total time for Observa-Dome personnel on-site: 12 days!

Friday

The installation crew from Observa-Dome would like to take this opportunity to thank
Scott Niskach; Orlando Science Center, Maynard Breeden; Baker Mellon Stuart, Peck, and
Marsha for their help and hospitality.